Climate & Environment
United States · Direct U.S. connection
Endurance Energy Generates First Net-Positive Power From Underwater Volcano
Seattle-based startup Endurance Energy successfully tested its subsea geothermal power plant, Adélie, generating net-positive electricity for 8.7 seconds at a peak of 16.5 kW from an underwater volcano off the Oregon coast in September 2026.
Share this article
THE PRIMARY BRIEF
- 01 · The primary finding
Endurance Energy successfully completed the first end-to-end demonstration of subsea geothermal power, generating net-positive electricity for 8.7 seconds from an underwater volcano off the Oregon coast.
- 02 · The primary evidence
On September 27, 2026, the company's Adélie plant produced a peak of 16.5 kW using heat from a natural hydrothermal vent at Axial Seamount.
- 03 · Why it matters
This achievement demonstrates a new pathway for continuous, baseload clean energy, which could offer energy independence for Pacific Rim nations and remote islands.
Seattle-based startup Endurance Energy achieved a significant milestone in September 2026, successfully completing a "proof point" test of its subsea geothermal power plant, Adélie. The plant generated net-positive electricity for 8.7 seconds, reaching a peak output of 16.5 kilowatts. This event marks the first end-to-end demonstration of subsea geothermal power.
This development matters because it offers a potential source of continuous, baseload clean energy that could reduce reliance on fossil fuels, particularly for remote islands and Pacific Rim nations. Subsea geothermal technology aims to provide consistent power, unlike intermittent renewable sources like solar and wind.
What the Records Show
The test took place at Axial Seamount, an active underwater volcano located approximately 300 miles off the coast of Oregon. Endurance Energy deployed its 3-ton geothermal generator, Adélie, at a depth of about 5,000 feet, which is approximately 1,500 meters. During the deployment, the company drilled the world's first offshore geothermal well. However, this newly drilled well proved too restrictive to power the plant as intended. To proceed, Adélie connected to a natural hydrothermal vent that was flowing at approximately 281°C (538°F). The test demonstrated the full chain required for subsea geothermal power, including drilling a well, operating a power plant on the seafloor, converting heat into electricity, and communicating with the system from a remote location. The power plant was operated in real-time from Seattle using a subsea fiber-optic network. During the net-positive run, the turbine reached about 26,000 rotations per minute. The operation was cut short due to a battery overcurrent protection system and a subsequent power cable failure during a restart attempt.
Timeline
Endurance Energy was founded in January 2025 by Andrew Redd, a former SpaceX engineer. The company made its first deep-sea deployment in August 2025. By June 2026, Endurance Energy had raised $63 million in total funding, which included a $54 million Series A round. This Series A round was led by Founders Fund, with additional investments from Felicis, Voyager Ventures, Riot Ventures, and Construct Capital, and continued support from Point72 Ventures, First Round Capital, and Ascend. The Adélie test at Axial Seamount occurred in September 2026. The company plans to deploy an upgraded system named Gentoo in winter 2026-2027. The ultimate goal is to deploy its first commercial 2-megawatt plant, Leopard, to deliver power in Tonga by 2027.
What Changed
The successful test of Adélie represents the first time a subsea geothermal plant has demonstrated net-positive electricity generation in an end-to-end system. This proof point shows the potential for harnessing heat from active underwater volcanoes to provide continuous, clean electricity. The company aims to make this technology a viable option for decarbonizing coastal regions around the Pacific and worldwide.
What the Subject Has Said Publicly
Andrew Redd, founder and CEO of Endurance Energy, stated, "On Sept. 27, we put a power plant on an active underwater volcano and made power". He also described the event as "our first end-to-end test," adding, "We now know, firsthand, what works at depth, what needs to be improved, and how to build the next system for sustained commercial generation". Redd also remarked, "Adélie made it exist, and now we know it's possible". He expressed his aim to pursue something that is both beneficial for the world and compelling from an employee perspective.
What We Could Not Confirm
We could not confirm the exact cause or detailed technical specifications of the power cable failure that ended the Adélie test. We also could not confirm the duration for which future systems are expected to generate continuous power, beyond the brief net-positive period of the Adélie test.